Announcement of the capacity reduction and replacement plan of the integration, reorganization and upgrading project of Xinjin Iron and Steel, Yongyang Special Steel and Zishan Special Steel
Release time:2023-10-18

  In accordance with the "Guiding Opinions of the State Council on Resolving the Contradiction of Serious Overcapacity" (Guo Fa [2013] No. 41), the "Opinions of the State Council on Resolving Excess Capacity in the Iron and Steel Industry to Achieve Relief and Development" (Guo Fa [2016] No. 6) and the "Implementation Measures for Capacity Replacement in the Iron and Steel Industry" (Ministry of Industry and Information Technology [2021] No. 46) requirements, Hebei Xinjin Iron and Steel Co., Ltd., Hebei Yongyang Special Steel Group Co., Ltd., Handan Zishan Special Steel Group Co., Ltd. will announce the capacity reduction and replacement plan of the integration, reorganization and upgrading project, and welcome the public to supervise. Contact number: 0311-87800210.

Construction project status
enterprise
name
construction
place
Smelting equipment Construction is to be started
Time
It is planned to be put into production
Time
replacement
proportion
remark
category Model unit equipment
quantity
Building capacity
(10,000 tons/year)
Hebei Yongyang Special Steel Group Co., Ltd Handan City
Yongnian District
Yongnian Special Steel Industrial Park
blast furnace 1260 cubic metre 1 116 In 2021
October
End of 2022 1.27:1  
hotplate 55 ton 1 41 2021年
10月
End of 2022 1.11:1  
Supporting the construction of 1 set of molten iron desulfurization facilities, 2 55tLF refining furnaces, 1 55tRH refining furnace, 1 55tVD refining furnace.
Exit from the project
serial number Province (autonomous region, municipality) The name of the business Smelting equipment Start the demolition time Demolition in place time remark
category Model unit equipment
quantity
Exit capacity
(10,000 tons/year)
1 Handan City, Hebei Province Hebei Xinjin Iron & Steel Co., Ltd 4#5#
blast furnace
450 cubic metre 2 104 Before completion and commissioning (planned 2022.12) Before completion and commissioning (planned 2022.12) 1.25:1
1# converter 40 ton 1 60 Before completion and commissioning (planned 2022.12) Before completion and commissioning (planned 2022.12) Among them, 225,000 tons will be used for the replacement of this project, with a replacement ratio of 1.25:1, and the remaining 375,000 tons will be used for the second phase of the Taihang Iron and Steel project
2 Handan City, Hebei Province Hebei Yongyang Special Steel Group Co., Ltd blast furnace 450 cubic metre 1 52 2017.7.26 2017.7.26 310,000 tons have been used for Yongyang Special Steel's relocation project, and the remaining 210,000 tons have been used for this project, with a replacement ratio of 1.25:1
hotplate 70 ton 1 30 2017.7.26 2017.7.26 200,000 tons have been used for the Yongyang Special Steel relocation project, and the remaining 100,000 tons are replaced, with a replacement ratio of 1:1
3 Handan City, Hebei Province Handan Zishan Special Steel Group Co., Ltd hotplate 35 ton 1 13 Before completion and commissioning (planned 2022.12) Before completion and commissioning (planned 2022.12) The displacement ratio is 1:1
4 Handan City, Hebei Province Wu'an Guangyao Casting Co., Ltd 3#
blast furnace
460 cubic metre 1 53 2017.12 2017.12 280,000 tons have been used for the remaining tasks in Wu'an City, 100,000 tons have been sold to Yuhua Iron and Steel, and 150,000 tons have been used for this project, with a replacement ratio of 1.5:1
5 Handan City, Hebei Province Hebei Xinwuan Iron and Steel Group Xinshan Iron and Steel Co., Ltd 1#
blast furnace
600 cubic metre 1 65 Before completion and commissioning (planned 2022.12)) Before completion and commissioning (planned 2022.12) Among them, 75,000 tons of production capacity will be used for this project, with a replacement ratio of 1.25:1, and the remaining 575,000 tons of production capacity will be used for the second phase of Taihang Iron and Steel Project
total 2.05 million tons of iron, of which 1.475 million tons were replaced, and 830,000 tons of steel, of which 455,000 tons were replaced. The remaining ironmaking capacity of 575,000 tons and steelmaking capacity of 375,000 tons will be used for replacement of other projects
INNOVATION ,CUTTING-EDGE TECHNOLOGY ,LEADING INDUSTRY DEVELOPMENT
LIGHT RAIL, HEAVY RAIL, CRANE RAIL, RAILS ACCESSARIES, I-BEAM/U-BEAM FOR MINING/TUNNELING PURPOSE, FLAT SPRING STEEL BAR, ROUND BAR, SQUARE BAR, BEARING/TOOL ROUND STEEL BAR.
Application industry: port and wharf, logistics and transportation, railway transportation, lifting machinery, mining, roadway, industrial production, chemical industry, non-ferrous metal smelting and processing.
Contact us →

Andy

Johnny

WeChat

WeChat

Johnny